title: "Inkster Data Center Stalls After Packed Council Meeting"
url: https://www.heredetroitmi.com/2026/10/20/inkster-council-takes-no-action-southern-street-data-center/
date: 2026-10-20T05:48:21-04:00
modified: 2026-10-20T05:48:21-04:00
author: "Melody Magana"
categories: ["Politics"]
site: "HERE Detroit"
attribution: "HERE Detroit"
---

# Inkster Data Center Stalls After Packed Council Meeting

> INKSTER, Mich. — A plan to turn an empty Inkster warehouse into a data center went nowhere Monday night after residents filled City Hall to speak against it and no City Council member offered a motion to approve the needed permit. Klever Technology Center LLC had asked for a special land use permit for the

*Source: [HERE Detroit](https://www.heredetroitmi.com/2026/10/20/inkster-council-takes-no-action-southern-street-data-center/) — October 20, 2026 by Melody Magana*

INKSTER, Mich. — A plan to turn an empty Inkster warehouse into a data center went nowhere Monday night after residents filled City Hall to speak against it and no City Council member offered a motion to approve the needed permit.

Klever Technology Center LLC had asked for a special land use permit for the 40,000-square-foot building at 27181 Southern St., which sits east of Inkster Road below Michigan Avenue. City planning papers put the investment at about $75 million for a site that would run around the clock with servers, cooling gear and backup power.

The Planning Commission had recommended conditional approval on Oct. 12. Even so, the request died without a vote.

The room reached capacity, leaving some people waiting outside. Speakers cited noise, light pollution and harm to the environment, and several said the property should go to a different kind of business.

The fight comes as server farms spread across southeast Michigan. Google got its final site plan through Van Buren Township in mid-October, Southfield cleared a Metrobloks project, and work is underway on a campus in Saline Township for Oracle and OpenAI.